Archive

Archive for the ‘Project 2007’ Category

Multiple cost rates for a resource in the same project

March 11, 2010 1 comment

Last week a question came up as to whether it is possible to have multiple cost rates for a resource within the same project.  The answer of course is yes, and this is how you do it.

1. Navigate to the Resource Sheet and double click on the resource you want to have multiple rates.

2. Navigate to the Costs tab of the Resource Information dialog

Costs 2

3. In the cost rate table, you can enter up to 5 different cost rates from A – E

Costs 3

4. Open the Resource Usage view and add the Cost Rate Table column

Cost 4

5. Change the Cost Rate Table entry to which ever cost rate you wish the resource to have for that task.

Cost 5

The web site specified is already linked to another project

October 30, 2009 Leave a comment

I ran into this issue whilst visiting a client this week, which I haven’t seen before. When the user tried to manually associate a project schedule with the workspace via Server Settings > Operational Policies > Project Workspaces , they would get this error:

The web site specified is already linked to another project

After verifying the workspace was not linked to an existing project, I turned my attention to the the project workspace template that we were trying to associate.  After a bit of searching around, it seems that the issue was caused by the site template used to create the project workspace being based on an existing site that was associated with a project schedule when it was saved. 

In order to fix the issue, it was necessary to:

  • Create a new Project site with the out of the box Project Workspace template;
  • Reapply any customisations;
  • Save the workspace into a new template;
  • Create a site using the new template
  • Associate the site with the schedule;
  • Migrate the contents from the old site to the new one;
  • Delete the old site.

Finally, the default project workspace template was updated to reflect the new fixed template using STSADM –o addtemplate  and changing the Project Workspace Provisioning Settings.

Free EPMU Training

October 15, 2009 Leave a comment
Categories: Project 2007 Tags: , ,

Inactive Tasks in Project 2010

October 8, 2009 8 comments

All too often when you are working on a project, the schedule can evolve from what you originally thought the schedule would be when you built it, to what the reality is. For example, in the schedule below there are three tasks, it turns out that Task 2 is no longer required.

clip_image001

In Project 2007 there are two options to remove the task…

Leave the task on the plan and set the remaining work to 0

clip_image002

This will have the effect of removing the effort from the task, but letting you see it existed (it also has the nasty side effect of turning the visual indicator into a milestone).

Delete the task from the plan

clip_image003

This will remove the task and effort from the schedule but not the baseline, so you run into an issue where you have a baseline figure that you can’t reconcile the tasks against easily.

Enter Project 2010 and Inactive Tasks. Inactive tasks allow the user to select a task and mark it as inactive, telling the scheduler to ignore the task and any associated effort. For example in the diagram below, task 2 has been made inactive.

clip_image005

Note the inactive task has been greyed out and struck through giving a visual indication that the task is inactive, but still allowing the user to see the original information against the task. As you would also expect, any tasks dependencies have reset to the project start date as Project doesn’t know how to schedule them.

If the task being set as inactive has actuals, Project will give us a warning dialog stating that the selected item has some actual values and do you want to delete it? If you select ‘Yes’, the time associated with the task will be removed from any summaries. It appears the actuals aren’t really deleted but just removed from any summaries and totals above.

Inactivate a task with actuals

clip_image007

Actuals removed from the project summary task:

clip_image009

The changes for inactive tasks don’t just manifest in the Gantt chart view, they are respected in all parts of Project 2010 where tasks are shown, including the Resource Usage view below:

clip_image010

On experimenting it also seems there is no restriction on where you can inactivate a task, the screenshot below shows what happens when you set the project summary task to be inactive, all the children become inactive automatically.

clip_image012

Finally as you would expect, Inactive tasks do not update the baseline, so there will be no impact on the variance calculations and you will still be able to see what made up the baseline.clip_image014

In conclusion, Inactive tasks are a very simple but useful feature in Project 2010 that users the world over are going to love.

Follow

Get every new post delivered to your Inbox.

Join 271 other followers